CompTIA E2C Project Certification Exam

Question No: 81 – (Topic 1)

Refer to the attached Exhibit.

Dumps4Cert 2017 PDF and VCE

Which of the following is the float of path Start-C-E-Finish in the network diagram?

  1. Zero

  2. One

  3. Three

  4. Five

Answer: A

Question No: 82 – (Topic 1)

Which of the following is the purpose of a Pareto diagram?

  1. To show the sequence in which work will be performed

  2. To create the process that will complete the project

  3. To determine the critical path

  4. To direct team efforts to the areas that will have the most impact

Answer: D

Question No: 83 – (Topic 1)

Two members of a team have had difficulty working together in the past. Which of the following should the project manager do to facilitate communication between the team members?

  1. Discuss the problem at the next project meeting and have the team members find a

    solution.

  2. Evaluate both members and replace the least important member.

  3. Speak with both team members and address concerns.

  4. Dismiss both team members and replace them with new members.

Answer: C

Question No: 84 – (Topic 1)

Which of the following is included in the project scope document? (Select Two).

  1. Quality metrics

  2. Work packages

  3. Assumptions

  4. Constraints

  5. Resource requirements

Answer: C,D

Question No: 85 – (Topic 1)

Which of the following is a benefit of the work breakdown structure (WBS)?

  1. It will provide a detailed budget for the stakeholders.

  2. Items not included in the project objectives can be added to the WBS for flexibility.

  3. It will ensure that scope creep will not occur.

  4. Contains all activities required to complete the project.

Answer: D

Question No: 86 – (Topic 1)

Transition plans include which of the following elements?

  1. Work Breakdown Structure (WBS)

  2. Project warranty

  3. Project process reports

  4. Earned value calculations

Answer: B

Question No: 87 – (Topic 1)

Which of the following occurs during a project kick-off meeting?

  1. Project plan approval

  2. Analyze project risks

  3. Identification of the stakeholders

  4. Project charter review

Answer: D

Question No: 88 – (Topic 1)

A project manager is conducting a root cause analysis with the project team. Which of the following tools should be utilized?

  1. Gantt chart

  2. Ishikawa diagram

  3. Network diagram

  4. Run chart

Answer: B

Question No: 89 – (Topic 1)

The project has been terminated. Which of the following should be conducted with the project team before they are released?

  1. Case study

  2. Feasibility analysis

  3. Stakeholder analysis

  4. Post-mortem analysis

Answer: D

Question No: 90 – (Topic 1)

A project manager conducted a risk probability and impact assessment with the project team. In which of the following risk management processes did this occur?

  1. Qualitative risk analysis

  2. Quantitative risk analysis

  3. Risk response planning

  4. Risk identification

Answer: A

100% Free Download!
Download Free Demo:JK0-017 Demo PDF
100% Pass Guaranteed!
Download 2017 Dumps4cert JK0-017 Full Exam PDF and VCE

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 Dumps4cert IT Certification PDF and VCE

Leave a Reply

Your email address will not be published. Required fields are marked *