Question No: 41 – (Topic 1)

Several managers are sharing a project team member, which is impacting the progress of both projects. Which of the following BEST describes the situation?

  1. Varying work styles

  2. Schedule variance

  3. Scope creep

  4. Competing resource demands

Answer: D

Question No: 42 – (Topic 1)

Which of the following occurs during a project kick-off meeting? (Select Two).

  1. Work performance information is established.

  2. Risk analysis is performed.

  3. Quality metrics are defined.

  4. Project goals are communicated.

  5. Roles and responsibilities of the project team are identified.

Answer: D,E

Question No: 43 – (Topic 1)

A project manager has failed to obtain the necessary permits from the local building commission. The project has been stopped because of a failure to understand the importance of:

  1. internal process compliance.

  2. risk avoidance.

  3. standards compliance.

  4. audit trail compliance.

Answer: C

Question No: 44 – (Topic 1)

A project budget has been reduced by 10 percent, but the project has a critical deadline. Which of the following should the project manager do FIRST to complete the project on time?

  1. Lower the quality standards for the finished product.

  2. Analyze the impact of the change.

  3. Eliminate 10 percent of the projects resources.

  4. Document the approved change request.

Answer: B

Question No: 45 – (Topic 1)

Key resources on a project are being shared. The stakeholders are aware of the shared resources and do not expect this to impact the progress of the project. In which of the following should the shared resource be documented?

  1. Quality management metrics

  2. Work Breakdown Schedule (WBS)

  3. Scope statement

  4. Risk register

Answer: D

Question No: 46 – (Topic 1)

Several key resources will be unavailable at the end of the project. The key stakeholders want to outsource the project to a third party. Which of the following risk responses is described in this situation?

  1. Risk avoidance

  2. Risk mitigation

  3. Risk acceptance

  4. Risk transference

Answer: D

Question No: 47 – (Topic 1)

A customer requests that the products quality be reduced to control its cost. Which of the following actions should the project manager take FIRST?

  1. Modify the project schedule.

  2. Obtain approval for the change.

  3. Reduce the amount of project resources to control costs.

  4. Modify the project budget.

Answer: B

Question No: 48 – (Topic 1)

Which of the following components are included in a communication plan? (Select Two).

  1. Statement of Work (SOW)

  2. Risk matrix

  3. Frequency

  4. Work Breakdown Structure (WBS)

  5. Distribution list

Answer: C,E

Question No: 49 – (Topic 1)

Which of the following documents is used when soliciting vendors?

  1. Request for Proposal (RFP)

  2. Work Breakdown Structure (WBS)

  3. Statement of Work (SOW)

  4. Responsibility Assignment Matrix (RAM)

Answer: A

Question No: 50 – (Topic 1)

Which of the following components is included in a transition plan?

  1. Ownership

  2. Quality metrics

  3. Project budget

  4. Quality baseline

Answer: A

100% Free Download!
Download Free Demo:JK0-017 Demo PDF
100% Pass Guaranteed!
Download 2017 Dumps4cert JK0-017 Full Exam PDF and VCE

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 Dumps4cert IT Certification PDF and VCE

Leave a Reply

Your email address will not be published. Required fields are marked *