Question No: 171 – (Topic 2)

The change control board approved a request for $25,000 to address rising labor costs of specialized trades. Which of the following documents should be updated?

  1. Scope statement

  2. Project schedule

  3. Resource requirements

  4. Project budget

Answer: D

Question No: 172 – (Topic 2)

Refer to the attached Exhibit.

Dumps4Cert 2017 PDF and VCE

Which of the following is the duration of the critical path in the diagram?

  1. 2

  2. 5

  3. 6

  4. 7

Answer: D

Question No: 173 – (Topic 2)

The frequency of measurement would be found in which of the following documents?

  1. Risk management plan

  2. Scope management plan

  3. Quality management plan

  4. Communication management plan

Answer: C

Question No: 174 – (Topic 2)

The project has been terminated prematurely by the organization. Which of the following will the project manager need to complete?

  1. Case study

  2. Cost benefit analysis

  3. Quality assessment

  4. Post-mortem

Answer: D

Question No: 175 – (Topic 2)

A project manager has finished the first phase of a project. Who of the following determines if the project continues?

  1. End users

  2. Project manager

  3. Project team

  4. Project sponsor

Answer: D

Question No: 176 – (Topic 2)

The project has an AC of $5,000. Which of the following would be used to determine the budget needed to complete the project?

  1. ETC

  2. PV

  3. BAC

  4. EAC

Answer: A

Question No: 177 – (Topic 2)

Which of the following skills would be the MOST useful in assembling an effective project team in a functional organization?

  1. Compromising

  2. Negotiation

  3. Estimating

  4. Padding

Answer: B

Question No: 178 – (Topic 2)

A project manager has been assigned two team members who do not get along. On past projects they have proven very difficult to work with and are often at odds with one another. Which of the following conflict resolution techniques would be BEST to address this?

  1. Forcing

  2. Avoiding

  3. Confronting

  4. Compromising

Answer: C

Question No: 179 – (Topic 2)

A project manager is receiving many requests for changes to a project. Which of the following did the project manager fail to complete?

  1. Proper project team selection

  2. Subject Matter Expert (SME) solicitation

  3. Milestone scheduling

  4. Stakeholder analysis

Answer: D

Question No: 180 – (Topic 2)

A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the following BEST describes the technique the project manager is using?

  1. Schedule optimization

  2. Fast tracking

  3. Resource management

  4. Crashing

Answer: D

100% Free Download!
Download Free Demo:JK0-017 Demo PDF
100% Pass Guaranteed!
Download 2017 Dumps4cert JK0-017 Full Exam PDF and VCE

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 Dumps4cert IT Certification PDF and VCE

Leave a Reply

Your email address will not be published. Required fields are marked *